Project Info

Bid Due Date: Thursday April 12, 2018 (2:00 am)

Apparent Low Bid: D & M Contracting

Bid Amount: $7,746,000.00

Bid Tab: View/Download

Awarded: Yes

Project Description:

The work includes construction of two options for the proposed raw waterline:

Option A includes +/- 12,225 LF of 30” ductile iron waterline, +/- 1,145 feet of 30” HDPE waterline by directional drill method, +/- 7,030 LF of 24” ductile iron waterline, +/- 135 LF of 30” ductile iron ball and socket waterline, +/- 285 LF of 24” ductile iron ball and socket waterline, +/- 460 LF of 48” steel casing by bore and jack method, +/- 65 LF of 48” steel casing by open cut method, and all other related appurtenances.

Option B includes +/- 19,115 LF of 30” ductile iron waterline, +/- 1,145 feet of 30” HDPE waterline by directional drill method, +/- 140 LF of 24” ductile iron waterline, +/- 320 LF of 30” ductile iron ball and socket waterline, +/- 100 LF of 24” ductile iron ball and socket waterline, +/- 460 LF of 48” steel casing by bore and jack method, +/- 65 LF of 48” steel casing by open cut method, and all other related appurtenances.

Cobun Creek Raw Waterline Drawings

Mandatory Pre-Bid: Wednesday March 7, 2018 (2:00 am)

Advertisement to Bid: View/Download

Plan Holders List: View/Download

Addendum:

Project Engineer: Cory Jones, PE

Email Address: cjones@mub.org

Bid Status: Current Projects