Street Repair Crew
- WVU hanger at the Airport - blacktop repair
- Marion St near Monongalia - road repair
- 924 Garrison - road repair
- 385 Charleston - road and ditch repair
- 87 King St - repair road around manhole
- 324 Demain Ave - sidewalk and road repair
- 241 Kingwood - road repair
- 215 Wagner Alley - road repair
- 713 South Hills Drive - driveway repair
Service Crews
- 1053 Maple Dr – New Sewer Service (Digging across the street)
- 38 Champagne Dr – Possible Water leak
- 540 Glory Barn Rd – split existing ¾ service
- 732 Snider St – Possible Water Leak (digging in the street)
- 382 Laurel St – replace storm culvert ( digging edge of street)
- 900 Hawthorne Ave – fix broken meter pit Digging in grass)
Storm Crews
- Grading the shop yard and laying drain pipe in back of yard so we can receive more fill
- Drop cleaning University Ave
Other Work
- Sewer cleaning crew will be cleaning the Deckers Grit Chamber
- Main line crews will be at the Dorsey Knob lift station #1 installing new wet well and pumps then moving to new sewer install Whisper Creek
- The 2nd main line crew will be relocating 8” water main at the WVU stadium then moving to the conduit install Kennedy Store Road for the Cobun Creek Dam #2 project