Cobun Creek Raw Water Line Construction Continues

On Monday, August 10th, MUB contractors will begin boring beneath Don Knotts Blvd. This work , which will be performed primarily from the water treatment plant area, will allow installation of 320 feet of 48” steel casing through which the 30” Cobun Creek raw water line will be installed. While the project will not disrupt traffic along Don Knotts Blvd, it does require temporary relocation of a portion of the rail trail until mid-September. A map approximating the temporary relocation of the rail trail is available by clicking here.