March 4th, 2025
North High Street work schedule
From now until Wednesday, March 5, Morgantown Utility Board crews will continue excavations along North High Street at points above Maiden Lane. This work will require moving lane closures along North High Street as work progresses. In addition, parking meters will be bagged along the work area.
Beginning Wednesday, March 5 through Thursday, March 13, MUB crews will replace a manhole at the intersection of North High Street and Prospect Street in front of Boreman Hall. This will require important adjustments to normal traffic flows:- North High Street will remain closed from the intersection with Prospect Street in front of Boreman Hall up to Maiden Lane
- The upper exit of the Mountainlair Parking Garage will be closed
- Traffic will not be permitted access to Prospect Street as it runs from North High Street toward University Avenue. To allow continued access to the Mountainlair loading docks, the area behind Stewart Hall, as well as the lower level of the Mountainlair Parking Garage, Prospect Street will open to two-way traffic entering and exiting from University Avenue.
MUB will begin relining the sewer pipe from Saturday, March 15 to Sunday, March 23. This will require lane closures as the relining progresses.
This work is being completed as part of the City of Morgantown’s Streetscape Project. Questions on MUB’s work can be directed to (304) 292-8443 or customer-service@mub.org.