News & Announcements

March 9th, 2020

MUB contractor to temporarily detour portion of rail trail

Beginning March 2, Morgantown Utility Board contractors will temporarily detour a portion of the rail trail while crews install a segment of the 30-inch raw water pipeline parallel to the trail. The detour will run roughly 750-feet near the Morgantown Water Treatment Plant and remain active until March 30th.

The raw water pipeline is an integral component of the 370 million gallon Flegal Dam and Reservoir being constructed along Cobun Creek Road. To date, roughly 18,000 feet of pipeline have been installed from the Flegal Dam and Reservoir.