​MUB Update – Baldwin Street

We have finished installation of stormwater pipe on Baldwin Street, having installed roughly 1,400 feet of 18” pipe and seven manholes. We are now finalizing work on a few storm drops and will begin road restoration following that. We expect road work to begin the week of July 27th and last three to four weeks.

Work at the University Avenue and Collins Ferry Road intersection will begin next week. When the traffic plan and work schedule is finalized with the West Virginia Department of Highways we will share the details.