Work schedule for April 29 to May 2

Main Line Work (new water line)

  • Beverly Avenue
  • Wilson Avenue

Service Crews

  • 433 Oakmont Court – ¾ New Water Service
  • Hoclar Stat Main St (Granville) – kill 2” feed
  • Grove St at Astor St – investigate sink hole
  • 437 Williams Rd – move meter
  • Work on the Westover Lift Station at Granville Bridge for City of Westover
  • 209 Morgan St – rebuild flushing system

Street Repair Crews

  • 816 Willowdale Rd - driveway repair
  • 31 LA Vista in Falling Waters - road repair
  • Fairchance Rd near state line - berm repair
  • Glory Barn Road - pour pad around pit
  • Main St in Granville - road repair
  • 413 Dunkard Ave - parking lot repair at Doug’s Towing

Vac Crew

  • Periodic cleaning at Cobun Creek Outflow
  • Baird St. Wet Well cleaning at Morgantown Industrial Park (MIP)
  • MIP Surge tank
  • Airport Blvd
  • Metro Pump Station
  • Ices Ferry
  • Glenmark Centre.

Video Inspection Crew

  • High St.
  • Callen Ave
  • Periodic on Brockway Ave.
  • Wayne Ave.
  • Spruce St.
  • Work on for record taps @ the Old Golden Blue (Jones Ave.)