Newsroom
News & Announcements
April 25th, 2019
Work schedule for April 29 to May 2
Main Line Work (new water line)
- Beverly Avenue
- Wilson Avenue
Service Crews
- 433 Oakmont Court – ¾ New Water Service
- Hoclar Stat Main St (Granville) – kill 2” feed
- Grove St at Astor St – investigate sink hole
- 437 Williams Rd – move meter
- Work on the Westover Lift Station at Granville Bridge for City of Westover
- 209 Morgan St – rebuild flushing system
Street Repair Crews
- 816 Willowdale Rd - driveway repair
- 31 LA Vista in Falling Waters - road repair
- Fairchance Rd near state line - berm repair
- Glory Barn Road - pour pad around pit
- Main St in Granville - road repair
- 413 Dunkard Ave - parking lot repair at Doug’s Towing
Vac Crew
- Periodic cleaning at Cobun Creek Outflow
- Baird St. Wet Well cleaning at Morgantown Industrial Park (MIP)
- MIP Surge tank
- Airport Blvd
- Metro Pump Station
- Ices Ferry
- Glenmark Centre.
Video Inspection Crew
- High St.
- Callen Ave
- Periodic on Brockway Ave.
- Wayne Ave.
- Spruce St.
- Work on for record taps @ the Old Golden Blue (Jones Ave.)