Listravia Avenue Sanitary & Storm Sewer Cured-in-Place Pipe Lining
Project Info
Bid Due Date: Thursday December 7, 2023 (2:00 pm)
Apparent Low Bid: Insight Pipe Contracting
Bid Amount: $67,280.00
Bid Tab:
Awarded: No
Project Description:
The work includes installation of cured in place pipe lining for approximately 545 feet of 8-inch clay sewer main and reinstatement of all service connections as well as installation of cured in place pipe lining for approximately 380 feet of 12-inch clay storm sewer main and reinstatement of all service connections.
Directions: Exit 4 off I-68 towards Sabraton. Head North on Route 7. Veer right onto Sturgiss Avenue. Turn right onto Dug Hill Road. Make first right onto Listravia Avenue. Project area is on Listravia Avenue from Dug Hill Road to Doyle Street.
Advertisement to Bid: View/Download
Plan Holders List: View/Download
Project Engineer: Ken Hacker, P.E.
Email Address: khacker@mub.org
Bid Status: Archive